What Inspections Are Required?

Construction financing involves two inspection tracks: lender draw inspections at build milestones and municipal building department sign-offs for code compliance. Expect foundation, framing, mechanical rough-in, and final inspections — plus an as-completed appraisal before permanent financing converts. Ryan and Steve map the full inspection path for Indiana new-build files.

Lender Draw Inspections vs. City Inspections

Before the first shovel hits dirt, an appraisal based on plans and specs establishes the as-completed value your loan amount depends on. Some lenders order a second appraisal at final completion to confirm the finished home matches projections.

During construction, the lender sends independent inspectors — separate from your builder and separate from the city — to verify work at each draw milestone. Foundation poured, framing complete, mechanicals roughed in, and final walk-through are common checkpoints before funds release.

Your local building department runs its own permit inspections for code compliance. A passed city rough-in does not automatically trigger a lender draw. Ryan and Steve coordinate both schedules so Indiana builders are not waiting on paperwork while crews sit idle.

At a Glance

Pre-buildPlans-based appraisal
Draw milestonesFoundation, framing, mechanicals
Lender roleIndependent draw inspectors
City rolePermits & code inspections
Final stepCO + completion inspection
Permanent loanAs-completed appraisal (sometimes)

Types of Inspections on a Construction Loan

Each inspection protects a different interest — loan collateral, code compliance, or final occupancy.

Draw inspections at milestones

The lender's inspector verifies completed work before each draw releases. Common stages include foundation, framing, rough plumbing and electrical, insulation, drywall, and final completion.

Municipal / building department

Local jurisdictions require permits and code inspections for structural, electrical, plumbing, HVAC, and fire safety. Failed city inspections must be corrected before the next phase proceeds.

Final inspection & Certificate of Occupancy

The building department issues a CO when the home meets all code requirements and is safe to occupy. Lenders require this before converting to permanent financing or releasing the final draw.

As-completed appraisal

Some programs require a final appraisal confirming the finished home value matches the original projections. One-time close products may use the initial plans-based appraisal; two-time close files often reappraise at completion.

How Inspections Gate Draw Payments

Inspections are the checkpoint between completed work and released construction funds.

Step 1

Builder completes a phase

Your contractor finishes an approved stage — foundation, framing, rough mechanicals, or finishes — and requests a draw from the construction account.

Step 2

Lender inspector verifies

An independent inspector confirms the work matches approved plans and the cost breakdown before the lender authorizes payment.

Step 3

City inspection passes

Parallel municipal inspections confirm code compliance. Both lender and city sign-offs may be needed before the next phase starts.

Step 4

Final sign-off & CO

After all scope items pass, a final lender inspection and municipal CO release remaining funds and clear the path to permanent financing.

Jul 21, 2026 • 2MG Daily

Construction Loans for Building Your New Home

Read article →

Frequently Asked Questions

What inspections are required before construction draws release?

Lenders typically require independent draw inspections at milestones — foundation, framing, mechanical rough-in, and final completion — before each portion of the construction budget is disbursed. The inspector verifies completed work matches the approved plans and cost breakdown.

Are lender inspections the same as city building inspections?

No. Municipal or building department inspections enforce local codes and issue permits. Lender draw inspections protect the loan collateral and may run on a different schedule. Passing a city rough-in does not automatically clear a lender draw — both tracks need attention.

When is a Certificate of Occupancy required?

Most jurisdictions require a final municipal inspection and Certificate of Occupancy (CO) before anyone can legally occupy a new home. Lenders also require a final completion inspection — and sometimes a final as-completed appraisal — before converting to permanent financing or releasing the last draw.

Does this page guarantee inspection requirements for my build?

No. Inspection schedules vary by lender, program, builder, and local jurisdiction. This page is educational only and is not a commitment to lend. Ryan and Steve outline the inspection path for your specific construction file before you break ground.